Project Assignment
Planning of a recycling yard with a collective problem waste area

Contractor
Administrative District Office

Our Services
Concept
Design planning
Authorization planning
Invitation to tenders
Contract award assistance
Construction engineering


Starting Situation
Miltenberg was chosen for the location of a process waste loading and unloading plant with adjacent recyc-
ling plant. In the waste loading and unloading plant, the refuse is pre-sorted, cut up and loaded for transpor-
tation to thermal processing. Recycling material and problem refuse from household and industry is accepted
at the recycling yard, sorted and put into interim storage.


Results
Planning and selection of suitable location: 1995 - 1998 Operation commencement: 1998

Facts and Figures
Planning and selection of suitable location: 1995 - 1998
Operation commencement: 1998