Project 
      Assignment 
      Planning and supervision assistance for equipping the administration 
      center.Contractor 
         
        Hilti AG, Schaan 
      Our 
        Services  
        Planning and engineering assistance in equipping the administration 
        buildings of the management center 
      Starting 
        Situation 
        The Hilti Deutschland GmbH has been located for many years 
        in Kaufering (the upper part of Bavaria). This 
        well-known company produces assembly equipment, primarily elements for 
        mounting and fastening techno- 
        logy. As part of the company's organizational development, it was decided 
        to centralize the main administ- 
        ration of the German branch in Kaufering.  
         
        Results  
        20 kV transfer station out of the Lech-Elektrizitätswerke 
        network; peak load approximately 700 kW; lightning 
        conductor and grounding system; electric installation with route systems; 
        lighting systems; interruption free 
        electricity supplying with a nominal capacity of 250 kVa for the telephone 
        and computer systems; informa- 
        tion and communication technology (telephone, fire alert systems, alarm 
        systems, clock and meter systems, 
        intercom systems, entrance control systems); building automation; EDP 
        network with active and passive  
        components; transportation technology (4 elevators); fire protection measures 
      
        Processing Time 
        1998 
      Facts 
        and Figures 
        
        
        13.6000 m² useable floor space  
          approximately 
        250 places of work  
          62 Mio DM total 
        building cost  
          700 kW electrical 
        junction capacity  
       
      < 