Project Assignment 
      Replacement 
      of the building control technology in the existing plant 1.9 in Aschheim, 
      near Munich. 
       
      Contractor 
      BMW AG Munich 
       
      Our Services 
        Planning 
        Invitation to 
      tender 
        Placement of 
      orders 
        Site supervisionScope 
        of Processing 
          MSR 
        / DDC- installations for the technical equipping of the building  
          Building control 
        technology center 
      
        Processing Time 
        1999 
      Starting 
        Situation 
        The existing installations for the building automation 
        at the BMW plant 1.9 in Aschheim were to be replaced with a modern, company 
        independent system. The modernization was to take place in such a manner 
        as not to impair normal operations.  
      Result 
        With the implementation of manufacturer-neutral, state-of-the-art 
        control technology, the control processes are more transparent and expenditures 
        for the system maintenance significantly lower.  
       
        < 