Project Assignment
Construction of a 40MW central heating unit in Munich-Riem for the supplying of the residential and
commercial buildings of the trade fair city Munich-Riem.


Contractor
Munich Department of Works

Scope of Processing
General planning services for the entire building technology, consisting of:

block type thermal power station module or alternative
implementation of geothermal plant 8 MW
control technology
electrical installations
technical building equipment

Processing Time
2001 thru 2003

Our Services
Planning
Invitation to tender
Placement of orders
Site supervision


Starting Situation
The Munich City Department of Works, SWM Versorgungs GmbH, are building a central heating unit at their
Riem location for the supplying of the trade fair city Riem with a total heat capacity of 40MW. The basic load
of approximately 8MW is to be covered by the utilization of geothermal subterranean water. If the basic load
can not be covered by geothermal energy, then the power load will be secured with the installation of 1 to 2
block type thermal power station modules.

Result
With the Riem heating center, a technical and economical system has been constructed that not only allows
for the implementation of geothermics but one that also most favorably satisfies today's environmental demands.