Project Assignment
Compilation of a complete energy and supply conceptContractor
Research Center Karlsruhe GmbH
Starting
Situation
The research center Karlsruhe has an infrastructure which
has evolved over 40 years and which will continue
to develop dynamically. Against the background of the liberalized supply
economy and within a planning
period of five years time, the project goal was the optimization and,
where necessary, new organization of the
central energy and media supplying of electricity, heat, refrigeration
and compressed air.
Processing
Time
October 1998 thru July 1999
Our
Services
Inventory of all media
Analysis of
energy supply contracts
Energy supplying
concepts
Financing models
Development
plan for the energy and media supplying
Supply
Requirements
Electricity: 110 GWh/a
Heat: 100 GWh/a
Refrigeration:
18 GWh/a
Compressed
air: 14 Mio. Nm³/a
Result
The concept was structured in four development phases;
the first step included measures for the optimization
of operations and contract conditions for media supplying. In the other
development phases, investment
measures for the area of production were investigated and analyzed. In
the process, cost saving measures
with an amortization time of less than three years could be developed
- measures which would lead to a
further 10% cost savings! Taking all interactions of the recommended measures
into consideration, the sum
of the realizable CO2 reduction was estimated to be about 28%.
<